阳江核电厂5、6号机组里程碑完成情况
完成日期
序号 里程碑
5号机组 6号机组
1 核岛FCD 2013–09–18 2013–12–23
2 常规岛FCD 2013–12–30 2014–05–13
3 核岛安装开始 2015–03–12 2015–11–11
4 核岛穹顶吊装 2015–06–12 2016–01–27
5 常规岛安装开始 2016–01–10 2016–08–01
6 核岛环吊可用 2015–10–14 2016–06–02
7 汽轮机首台低压缸模块到货 2016–04–17 2017–03–03
8 发电机到货 2016–11–06 2017–08–14
9 泵站进水 2016–11–30 2017–07–18
10 反应堆压力容器与蒸汽发生器全部到货 2016–09–30 2017–09–06
11 核岛主回路冷试开始 2017–07–21 2018–10–23
12 核岛主回路热试开始 2017–12–08
13 开始装载核燃料 2018–04–20
14 首次核临界 2018–05–20
15 首次并网 2018–05–23
16 具备商业运行条件 2018–07–12